Information portal on various topics of management of public resources of the Portuguese State

Project sheet

Name

Implementação de medidas de eficiência energética no edifício da Geocontrole

Total project amount

124,36 thousand €

Amount paid

65,24 thousand €

Non-refundable funding

124,36 thousand €

Loan funding

0 €

Start date

04.05.2022

Expected end date

30.04.2023

Dimension

Climate Transition

Component

Energy efficiency in buildings

Investment

Energy efficiency in buildings used by the service sector

Operation code

01/C13-i03/2022.P299

Summary

"A Geocontrole Geotecnia e Estruturas de Fundação, S.A. (NIPC 500 126 321), doravante Geocontrole, foi constituída em 1975 e é hoje uma das principais empresas no panorama geotécnico em Portugal (CAErev3 principal 71120 - atividades de engenharia e técnicas afins).A empresa desenvolve a sua atividade comercial num Grande Edifício de Comércio e Serviços existente, situado em Lezíria do Saldanha, 2695-444 Bobadela LRS, do qual é proprietária (possui contrato de arrendamento, detém o sistema de climatização e seus consumos, é titular das faturas energéticas e tem autorização expressa da titular para realizar intervenções no edifício).É agora sua intenção realizar um investimento de 177.650¬ , no período compreendido entre 04-05-2022 e 30-04-2023, no âmbito do presente projeto, para reconverter os seus sistemas energéticos, baixando o consumo e melhorando os outputs de serviço. O projeto incidirá sobre 3 tipologias de intervenção, iniciando-se com o desenvolvimento de auditoria energética ex-ante da responsabilidade do Perito Qualificado, Filipe Rocha Rodrigues (PQ02385), a fim de caracterizar a situação no cenário de referência, propor medidas de utilização racional de recursos e proceder à emissão do certificado energético. De facto, prevendo melhorar a eficiência energética, e permitir que o edifício passe de uma classe energética C para uma mais eficiente - A, serão implementadas várias medidas. Nestas inclui-se a intervenção em sistemas técnicos, mais concretamente a substituição, de forma integral, de luminárias existentes por umas de elevado rendimento luminoso. Por outro lado, far-se-ão ainda investimentos na tipologia de intervenção ""produção de energia com base em fontes de energia renováveis para autoconsumo"", designadamente a instalação de UPAC de painéis fotovoltaicos de 43,2 kWp e atuações ao nível da climatização (ex. bombas de calor).Por fim, considerou-se a realização de auditoria energética ex-post e respetiva emissão do certificado energético, comprovando o alcance dos objetivos propostos, associados à realização do projeto, para o ano de conclusão do projeto: Redução anual do consumo de energia primária nos edifícios: 15"

Beneficiaries

Within the scope of the Recovery and Resilience Plan, two types of beneficiaries are responsible for carrying out the projects and using the funding provided. Due to their similar role, the reference to these two types of beneficiaries has been simplified and unified under the term "Beneficiary".
The two types are::
  • Direct Beneficiaries are those whose funding and projects to implement are part of the Recovery and Resilience Plan that has been negotiated and approved by the European Union;
  • Final Beneficiaries are those whose funding and projects to implement are approved following a selection process through Calls for Applications.

Call for applications

As part of the Call for Applications, submissions are requested to select the projects and final beneficiaries to whom funding will be awarded. Specific selection criteria are defined for each call, which must be reflected in the applications submitted and assessed.

The project is appraised on the basis of its compliance with the selection criteria laid down in the calls for applications, and a final score may be awarded, where applicable.

Final evaluation score

3,0
Important note

The components for calculating the assessment score can be found in the selection criteria document mentioned below.

Selection criteria

The funding selection criteria to which this project and its final beneficiary were subject and its score can be found in detail on the Recuperar Portugal platform.

Beneficiaries

Intermediate beneficiaries

Beneficiaries

Procurement

Beneficiaries representing public entities implement their project by signing one or more contracts with suppliers for goods or services through public procurement procedures.

To ensure and provide the utmost transparency in all these contracts, a list of the contracts that were signed under this project is available here, along with the information available on the Base.Gov platform. Please note that, according to the legislation in force at the time the contract was signed, some exceptions do not require the publication of the contracts signed on this platform, and, therefore, no information is available in such cases.

Geographic distribution

124,36 thousand €

Total amount of the project

Percentage of the amount already paid for implementing projects

, 52,5 %,

Where was the money spent

By county

1 county financed .

  • Loures 124,36 thousand € ,
Source EMRP
09.03.2026
All themes
Transparency without leading