Name

"EstágiAP XXI - 2ª Edição"

Total project amount

611,99 thousand €

Amount paid

578 thousand €

Non-refundable funding

611,99 thousand €

Loan funding

0 €

Start date

03.01.2023

Expected end date

07.10.2025

Dimension

Digital Transition

Component

Digital public administration

Investment

Empowering public administration to generate real public value

Operation code

04/C19-i07.05/2022.P447

Summary

Considerando que o estágio profissional tem por base o desenvolvimento de uma experiência prática em contexto real de trabalho com o objetivo de promover a inserção de jovens licenciados no mercado de trabalho, de acordo com as suas competências académicas, e traduzindo-se o estágio numa forma de transição de indivíduos para a vida ativa, as ações a desenvolver no âmbito do presente projeto centram-se, essencialmente, na formação de novos talentos, designadamente ao nível do desenvolvimento das suas competências técnicas, por via do contacto com a realidade profissional da sua área de formação académica, possibilitando uma verdadeira conciliação da teoria com a prática.Sublinhar ainda que no âmbito deste programa de estágios, há que destacar uma das fortes ações a desenvolver para além da componente formação, será a promoção de uma sólida interação com profissionais da DGRSP bastante experientes nas suas várias áreas de atuação, contribuindo, não só para criar rotinas de trabalho no estagiário, como também proporcionar o seu desenvolvimento técnico e pessoal, ajudando-o a trabalhar as suas soft skills;

Beneficiaries

Within the scope of the Recovery and Resilience Plan, two types of beneficiaries are responsible for carrying out the projects and using the funding provided. Due to their similar role, the reference to these two types of beneficiaries has been simplified and unified under the term "Beneficiary".
The two types are::
  • Direct Beneficiaries are those whose funding and projects to implement are part of the Recovery and Resilience Plan that has been negotiated and approved by the European Union;
  • Final Beneficiaries are those whose funding and projects to implement are approved following a selection process through Calls for Applications.

Call for applications

As part of the Call for Applications, submissions are requested to select the projects and final beneficiaries to whom funding will be awarded. Specific selection criteria are defined for each call, which must be reflected in the applications submitted and assessed.

The project is appraised on the basis of its compliance with the selection criteria laid down in the calls for applications, and a final score may be awarded, where applicable.

Final evaluation score

16,0
Important note

The components for calculating the assessment score can be found in the selection criteria document mentioned below.

Selection criteria

The funding selection criteria to which this project and its final beneficiary were subject and its score can be found in detail on the Recuperar Portugal platform.

Beneficiaries

Intermediate beneficiaries

Beneficiaries

Procurement

Beneficiaries representing public entities implement their project by signing one or more contracts with suppliers for goods or services through public procurement procedures.

To ensure and provide the utmost transparency in all these contracts, a list of the contracts that were signed under this project is available here, along with the information available on the Base.Gov platform. Please note that, according to the legislation in force at the time the contract was signed, some exceptions do not require the publication of the contracts signed on this platform, and, therefore, no information is available in such cases.

Geographic distribution

611,99 thousand €

Total amount of the project

Percentage of the amount already paid for implementing projects

, 94,4 %,

Where was the money spent

By county

1 county financed .

  • Lisboa 611,99 thousand € ,
Source EMRP